What does First-pass yield measure?

Prepare for the CIMA Managing Performance (E2) Exam. Practice with flashcards and multiple-choice questions, each with explanations. Get ready for your exam!

Multiple Choice

What does First-pass yield measure?

Explanation:
First-pass yield measures the proportion of units that pass quality checks on the first attempt, without needing any rework. It is calculated as the number of units that exit the process after the first pass divided by the total number of units that entered the process. A high FPY shows the process is effectively producing good quality units without rework, while a low FPY signals more defects requiring rework and higher costs. This is different from defects-per-million, which counts defects rather than whether a unit passed first time; it also isn’t about production stoppages or inventory levels, which are separate performance measures.

First-pass yield measures the proportion of units that pass quality checks on the first attempt, without needing any rework. It is calculated as the number of units that exit the process after the first pass divided by the total number of units that entered the process. A high FPY shows the process is effectively producing good quality units without rework, while a low FPY signals more defects requiring rework and higher costs. This is different from defects-per-million, which counts defects rather than whether a unit passed first time; it also isn’t about production stoppages or inventory levels, which are separate performance measures.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy